A reader asked us about how soon National Development will get going on its housing/retail/office project on the old Grossman’s lot on Washington St. in Wellesley. National Development tells us that the company hopes to prep the site this summer but that there’s no hard schedule set. There are about 10-12 weeks of work needed to get the site ready before construction starts. Best case scenario: Construction starts in October.